Environmentalists protest hydropower plant construction plan

12:21 • 16.10.12

The environmental group, which earlier campaigned for the protection of the green areas of Teghut (Tavush region) and the Khosrov reserve (Ararat region), calls for urgent measures to suspend the licenses for the construction of small hydropower plants across Armenia.


In a letter to Minister of Nature Protection Aram Harutyunyan and Prime Minister Tigran Sargsyan, the activists stress the need of considering the lawfulness and the environmental and economic damages of the activities carried out so far.


“With a statement issued five days ago - October 11, 2012 - several environmental civil groups proposed requirements for the so-called small hydropower plant construction plan, specifying timeframes for their implementation.


Following a discussion at the Nature Protection Ministry later the same day, the minister issued an instruction for creating a working group, which was supposed, within a 10-day period, to study the questions relating to the constriction of the small hydropower plants Khachaghbyur 1 and Khachaghbyur 2 in the Getahovit community


As part of its efforts to issue permission for the construction of the above power plants, the working group has to study at least:


a) The lawfulness of the of experts’ environmental impact assessment activities in the small hydro-power plants Khachaghbyur 1 and Khachaghbyur 2, and the minister’s conclusion.


b) The environmental and economic damages caused to the Republic of Armenia and the Getahovit community as a result of unlawful activities by state officials and private companies,” reads the letter.


Insisting on their demand to suspend the construction licenses, the environmentalists further call for the elaboration of a justified environmental and socio-economic impact assessment methodology and a subsequent reassessment of the small hydropower plants’ permissibility based on the new comprehensive standards.”