Accident, in the energy system: Yerevan Thermal Power Plant and Hrazdan 5th Block Closed, Yerevan Metro Operation Suspended, All Passengers evacuated
Electricity fluctuations have been registered in different parts of Yerevan on July 10 at around 1 pm. The Crisis Management Center informed that operative groups are working in people's crowded places, especially in subway.
RA Deputy Prime Minister Tigran Avinyan informed on his Facebook page that there is an accident in the energy system in Armenia. Electricity shutdowns are possible.
"At the moment we have an accident in the energy system. Yerevan Thermal Power Plant and Hrazdan 5th block are off. Shutdowns in the Republic are possible. The work is being done so that the problem will be settled till 7 pm ", says the RA Deputy Prime Minister.
Yerevan Metro reported that due to power fluctuations electric power supply across the subway completely interrupted. In some parts, trains remain in tunnels. Hakob Karapetyan, press secretary of Yerevan municipality, wrote this on his Facebook page.
"Then the electricity partially restored, the trains on the route approached the stations where the passengers were evacuated. At the moment, the train, which runs from the Zoravar Andranik station to the Republic Square, is in the tunnel.
The situation is under control. Prior to the regulation of electricity issues, the work of the subway will be suspended, "Hakob Karapetyan wrote.
"At the moment there are no trains in the tunnels, all passengers have been evacuated," Hakob Karapetyan added.